You don’t need a connection to use Pembris Electrical on site. After activating with your administrator’s code, or loading their licence file, the tools keep working offline for up to three weeks by default.
How long you can stay offline
- Offline period
- 21 days by default
- Never past
- The grace period after your company’s subscription ends
The licence dialog shows Works offline until: the last day the tools work without a connection. Open it from My settings › Licence › Manage licence….
Before you go offline
Connect to the internet
On the PC you will take on site.
Open the licence dialog
My settings › Licence › Manage licence…
Click Renew now
The licence renews. Check the new Works offline until date.
When the date gets close
- With 3 days or less left, the licence dialog opens once a day when Revit is idle.
- Connect and click Renew now, or let it renew quietly the next time the PC is online.
- On a PC that is never online, ask your administrator for a new licence file.
Pilot builds
A pilot build works offline with no licence until its last working day, which the Licence page and dialog name. At midnight, Oslo time, at the end of that day its tools stop; a change being written at that moment is rolled back and says why.